Question

My neighbour who is a registered builder has this week started excavations of his drive to provide a side extension to his property. He has not issued a Party Wall act Notice. When approached about the excavations being within less than 1 metre of my property he became very aggressive.

The property concerned is a brick garage which was an adjoining garage, my neighbour took his side down without asking permission and left my wall which was the internal wall as open brease block and no side to the garage at the top, so he has already caused damage.
 
I have the concern now that the Party Wall Act was not issued and he will cause more structural damage as he is digging lower than my garage foundations. Am I wasting my time taking this any further?

Answer

I would not say that you are wasting your time taking this any further but it may be that you need to take legal action. I would start with a letter from an experienced local Party Wall Surveyor or a solicitor pointing out to him that the work comes within the scope of the Act and you should be served with a notice. It may be necessary to threaten an injunction to make him take notice.

If he ignores the letter you will have to decide whether you are happy to pay the up front legal costs of an injunction and claim them back later. Should he come on to your land without serving a notice he will be trespassing.

If he thinks that you intend to enforce your rights he may decide it is best to follow the correct procedures.

Question

My neighbour is building a brick garage on the side of his house and the external wall will be 15cm (fifteen cm) from the boundary line. The plans state that the foundations will go up to the boundary line. The building will create a small alleyway between his and our side walls. There is exactly enough room up to the boundary line on our side for us to take our black wheelie bin down the passage. 

We intend to gate the alleyway for extra security but this leaves a gap on his side of the boundary line of 15cm. He intends to run his downspouts for gutter water onto the outside of his external side  wall into the alley and into a grid presumably. Can he do this with only 15cm knowing that he will have no access to his downspouts or grids? His proposed garage extension allows him no access to his back garden as he has left only a strip of 15cm (presumably for overhang of gutters and soffits).

Answer

An owner can build right up to their boundaries including the airspace above their land. This will not, however, provide your neighbour with a right of access in future to maintain rainwater fittings etc. If such access were required, and you were unwilling to grant it your neighbour would have to obtain a court order under the access to Neighbouring Land Act 1992.

There is also the issue of access to build the garage – if the work does not come within the scope of the Party Wall Act access would only be with your consent and the Access to Neighbouring Land Act cannot be used for new work; only maintenance. The work will come within the scope of the Party Wall Act if the foundations for the garage are within 3 metres of your property and deeper than your foundations. If that is the case your neighbour should serve you with a Notice of Adjacent Excavation.

Question

I am planning to make a side infill extension (pitched roof) to my terraced property. There is a brick wall between the neighbouring property and mine, serving as the boundary wall between us. Obviously for my new extension I will have to break that wall and make a new wall which will be a part of my extension/new room. I know that I need to serve a party wall notice to my neighbours but after going through the official documents relating to party wall notices I am not sure which notice I need to serve.

Will it be for making a new wall astride the boundary or just next to the boundary within my site, or will it be for excavations as there will be some excavation happening to put in the trench foundation? How do I know that my foundation will be deeper than theirs? You said somewhere in your post that it’s guess work but how do I guess if I do not have a clue about the depth of foundations for such houses. They were built in 1880 I think.

Answer

If the boundary wall is shared it is what the Act refers to as a Party fence Wall. You have the right to demolish a party fence wall and rebuild it as a party wall forming the side of your proposed extension. You should serve a party structure notice referring to section 2(2)(l) of the Act.  The foundations to a property built in 1880 will probably be just some corbelled bricks so the foundations to your new wall will be deeper. You will therefore have to serve a second notice, a Notice of Adjacent Excavation, referring to section 6(1) of the Act.

This online tool may be some help with drafting the notice – http://www.mypropertyguide.co.uk/partywall/notice/generator 

Question

Can you please advise if I can ask my surveyor to include asking my neighbour for the Building Regulations Approval details and the name & insurance details of the builder in the Party Wall Agreement?

Answer

Most party wall Awards will include a clause stating that the notified work should comply with all statutory requirements, including the Building Regulations – that is a requirement of the Act. Your surveyor could go further and request that a copy of the completion certificate from Building Control is provided to him at the end of the works but that would be his decision. 

There is also normally a clause stating that the Building Owners are to maintain or cause contractors to maintain adequate insurance against risks such as damage but ultimately such things are the Building Owner’s responsibility. Where there has been damage the surveyors would deal with it under the Act i.e. arrange the contractor to make good or agree compensation (that will be your choice) so unless it was very significant damage the insurance wouldn’t come in to it. Many surveyors would request to see a copy of the contractor’s insurance policy but again that has to be your surveyor’s choice.

You have appointed your surveyor to deal with the dispute on your behalf so as long as he is working with the Act he should be left to do that how he sees fit.

Question

In relation to the question asked below :
 
How Far Back From the Line of Junction Should I keep my New Wall to Avoid Serving a Section 1 Notice?
 
The Question above had existing foundations in place. If you didn’t have existing foundations in place, how could you go about extension design to avoid having to serve notice. 

e.g. Neighbours extension might have 600mm depth foundation, which would limit the householders depth to 600mm, could an eccentric foundation or solid slab then be used at that depth and the building line set back the 2-3 inches from the boundary line as you suggest in the original answer?

Left side Neighbour, right side proposed extension as p

xxxxxxx   pppppppp
x             x p             p
x             x p             p
xxxxxxxxOxxxxxxx
x                x              x
x                x              x
x                x              x
 
Also a new question (I think), at the point marked on the diagram “O”, ie my back wall past both the centre line of the main party wall, and the brick either side, ie the full thickness. In building an extension you would probably use a metal wall starter, is this classed as a party wall, in that its the same wall that extends all the way across the back of the house or is it only a dividing wall and any part of it.

Answer

Using a raft foundation would be one way of avoiding the need for a Section 6 notice – as long as you don’t need to excavate deeper than the base of your neighbour’s foundations Section 6 is not invoked. 

There’s no clear answer to the wall starter question. It comes down to whether the party wall ends at the internal or external face of the rear wall. We tend to include it on a party structure notices where other Section 2 works are being undertaken but personally the risk of damage is so low that I would not serve notice just for a wall starter. Also, if you are keeping back from the line of junction to avoid a Section 1 notice the wall starter will be barely over the line of the party wall.

Question

I moved into my property several years ago and only noticed a couple of years ago that the adjoining wall (at the front)  to our properties has been built on my side of the boundary. The neighbour said it was difficult to dig the concrete out when they were laying the drive and the owner of my house at the time had agreed to the wall being built over on my side  / my property

The neighbour is fine about it and said he is happy for sign over the wall to me  – is this the best thing or the right thing to do to protect my rights and preserver the original boundary  (the boundary wall has been in place for about 11 years, so can this affect where the boundary lies over time) and what sort of agreement would I need – a standard party wall agreement ?  

Answer

This isn’t a party wall matter so not  something that we cover on www.partywalladvide.com

From your description it seems that you predecessor gave his consent for the boundary to be moved. If that was not confirmed in writing then it would be up to your neighbour to claim adverse possession.  As he seems willing to sign the wall over to you there shouldn’t be an issue but I would recommend that you get the deeds updated to reflect this change. 

Like I say though, this is not our specialist area so you should really have a chat with a solicitor.

Question

Please can you let me know under which circumstances a SOC must be undertaken by a residential party wall surveyor?  Is it in fact a requirement?

Answer

It is not mandatory to have a schedule of condition attached to a Party Wall Award although it is considered to be good practice. The only scenario in which it would not be is if the Adjoining Owner refused to provide access – even then we would look to schedule the relevant exterior parts from whatever vantage point we could use.

Question

My neighbour is refusing to supply a copy of a ‘Party Wall Agreement”. In the beginning I complained that I did not want my neighbour to build his extension I then found it was a permitted development extension. Upon hearing that I had no ability to stop him I gave up.  He then sent me a copy of the party wall agreement after getting it sorted out by surveyors and had everything drawn up and in place. He went ahead with the work. Now I want to sell the terrace house I find I need a copy of this agreement and the only one is with the neighbour who years later is still upset an refuses to supply me with a photocopy. What can I do to get a copy,  and do I need this to sell the house?

Answer

If by ‘Agreement’ you mean an Award produces by appointed surveyor(s) then your should have been served a copy at the time. If you contact the surveyor that you appointed he should still have a copy. If you consented to the works then all there would be is a signed consent form – if that is the case then nobody other than your neighbour will have one if you didn’t keep a copy. I doubt very much  that it will prevent you selling the property.

Question

Following a party wall dispute and after exchanging some correspondence with the Adjoining Owner’s surveyor, I decided not to proceed with the notifiable works. However, the said surveyor then sent me an invoice for the work he had accomplished for the surveyor.
 
I have been advised by my own party wall surveyor that the Building Owner is obliged to pay for the Adjoining Owner’s surveyor fees only if an Award is reached.
 
If this is always the case, where can I find supporting evidence for it?

Answer

There is no supporting evidence for your surveyor’s view as the Act does not cover what happens when the Building Owner changes their mind and does not complete the work. I am not aware of any relevant case law on the subject either. 

Most surveyors take the view that if a notice has been served there must be an Award; an Award in those circumstances would simply state that the works have been abandoned and cover the surveyor’s fees. If your Adjoining Owner’s surveyor takes that route his fees will increase further to cover the time to agree, sign and serve the Award – if he is happy to just invoice you for the time he has expended to date you may be wise to accept that. 

Personally I can’t understand your reluctance to pay, he obviously acted in good faith to deal with a matter that you instigated by serving a notice.

Question

My garden and my neighbours garden is separated by a fence. We are intending to build the wall of our new extension alongside this fence, entirely on our land, without removing the fence. On the neighbours side of the fence, there is garden (not buildings). What section of the Act is applicable?

Answer

You will need to issue a Line of Junction notice if your wall is being built up to the boundary (but wholly on your own land) or if the foundations to the proposed wall project beyond the boundary.  If the fence is on the boundary then I assume your wall will be set back slightly from the boundary so no notice will be required.